Things to Keep in Mind (TKM) Before Tile Installation:

  • Before starting tile installation work at plinth level, make sure that proper compaction of soil layer has been carried out.
  • Also ensure that sub floor of PCC, RCC, or brickbats have been done with proper levelling with slope if required.
  • Brick masonry and plaster work of all the rooms should have been completed.
  • The wall tile should be installed first before you start laying the floor tiles.
  • Waterproofing should be completed first if specified in drawing or tender.